German regulator's grid fee decision 'restores investor confidence' in energy storage market
The German network regulator's decision to maintain grid fee exemptions for battery storage "ensures that billions in private investment remain directed" into the market.
Last week, German newspaper Handelsblatt reported that the president of the Bundesnetzagentur (BNetzA), Germany's Federal Network Agency, had confirmed the exemption would remain in place for battery energy storage system (BESS) projects coming online by 4 August 2029.

While the exemption on fees levied for use of the transmission grid had been guaranteed for a 20-year period after project commissioning, it emerged earlier this year that BNetzA was considering removing it, as part of a broader reform of grid fees.
Grid fees could even have been applied retrospectively to existing projects. In February, Energy-Storage.news heard that the proposal instantly brought uncertainty and investment caution into a market that had, until then, been "going through a very positive development," from Julian Jansen, managing director for Germany at BESS technology provider Fluence.

While projects that are commissioned by 4 August 2029 will remain exempt, they must reach final investment decision (FID) before new regulations under the regulator's AgNeS grid fee reforms come into effect. The agency is expected to introduce dynamic grid fees for energy storage at some stage during 2030 and 2033, and will give more info this year.
Confirmation of the exemption "restored confidence in existing and short-term investments," while in proposing a dynamic regulation for grid fees over the longer-term, BNetzA had "taken a significant step towards recognising the specific role of battery storage in the power system," Jansen said.
However, the market still needs "clarity and practical rules" regarding grandfathering and the definition of FID, so that existing and near-term projects can meet the requirements to qualify for the exemption before the 2029 cut-off date, he said.

"Storage projects often require substantial development work long before formal FID is taken. Developers secure land, pursue grid connections, prepare permits, structure financing and negotiate supply agreements. If the FID threshold is set too narrowly, advanced projects could fall outside the protection, even though significant capital and effort have already been committed. That would create uncertainty at exactly the point where Germany needs investment momentum," Jansen said.

"According to the current proposal, grid-connected storage would not face work-based grid charges, and there will be no double charging for withdrawal and injection. Instead, the Bundesnetzagentur proposes a low capacity-based charge, aligned with the proposed charge for generators," Jansen said.
"This is a constructive proposal. At this level, the future grid fee should not materially weaken the business case for battery storage in Germany. Market analysis indicates that such a charge would reduce project IRRs by around two percentage points. For projects expected to reach commercial operation after 2029, this would generally keep projects within an investable range. In other words, the capacity charge itself is not the main concern."

The industry now awaits the publication of the formal draft regulation this summer. Jansen argued that the industry's priority should be to interpret the "constructive direction of travel" into a clear and workable set of rules. This is particularly so when it comes to grandfathering and FID criteria, which he said must reflect how energy storage projects are developed, financed and procured.