UK Battery Storage Development Enters the Execution Phase
The UK market experienced high levels of interest and activity throughout 2025, but is now showing signs of moving away from a development-led phase toward one centred on project delivery and execution. Despite wider global momentum in energy storage, the UK market has remained resilient and active.

As an early adopter of large-scale energy storage systems, the UK is among the more mature markets in Europe. As a result, growth in pipeline capacity and future operational capacity is expected to progress at a steadier pace compared with newer European markets that are still scaling rapidly.
Recent changes to grid policies have played a significant role in shaping market dynamics this year, highlighting the extent of congestion within the grid connection queue. This article explores key developments across the UK energy storage landscape in 2025, drawing on detailed analysis of project pipelines and completed assets.

Fig 1: Grid reforms played a large part in the turbulent quarterly application pattern from Q4' 24 onward.
Looking across the full year, 2025 recorded the highest level of submitted capacity to date, exceeding 96GWh, around 25% higher than in 2024. The second quarter surpassed Q4 2024 to become the strongest quarter by submitted capacity. However, Q4 2024 still holds the record for the highest number of applications submitted overall.
That surge was largely driven by grid reforms that required projects to enter planning before the end of 2024 to qualify for a later-stage grid connection.

This deadline effect made the typical slowdown in first-quarter submissions more pronounced in 2025. The peak in Q2 2025 was supported by several very large projects being submitted, reinforcing a broader shift in the UK toward higher-capacity developments. Average submitted project size rose to more than 400MWh in 2025, compared with 257MWh the previous year.
Interest in long-duration energy storage also increased, with multiple projects extending beyond the standard two-hour duration and targeting up to five hours.

This trend has been partly encouraged by the introduction of a new revenue support mechanism aimed at longer-duration assets. While July saw the highest number of applications, May accounted for the largest share of capacity, with more than 20% of the year's total submitted in that single month.

Activity declined sharply in the latter part of the year, with submissions falling by 91% quarter-on-quarter.
This drop may reflect the passing of key submission deadlines and heightened uncertainty while market outcomes were still pending. Despite this slowdown, the high volume of applications submitted in the previous year, particularly toward the end of 2024, contributed to a greater number of planning decisions being issued in 2025.
Around 78% of projects submitted in 2024 have since received decisions. Submitted and approved capacities show a weak positive correlation of approximately 0.58, suggesting that peaks in activity tend to align broadly over time.

Regionally, Scotland recorded the largest total submitted capacity. Focusing solely on England, which accounts for more than 80% of the UK's operational capacity, the East Midlands led both in 2025 and overall.
In the eastern part of the country, projects were more likely to be co-located with solar generation, with around half of submissions combining the two technologies. This contrasts with the North West, where only about 10% of submitted projects were co-located with solar.